- Permitting Under the Clean Air Act Total results: 19
- Air Emissions Inventories Total results: 34
- Asbestos Total results: 141
- Butte Area/Silver Bow Creek Total results: 17
- Coronavirus (COVID-19) Total results: 33
-
East Palestine, Ohio Train Derailment
Total results: 148
- Waste disposal and containment Total results: 13
- About the Cleaning Process Total results: 10
- About the East Palestine Train Derailment Total results: 13
- After Cleaning Total results: 3
- Air testing Total results: 2
- Assistance with Child Care and Pets During Cleaning Total results: 2
- Chemicals of concern and associated health impacts Total results: 8
- Eligibility Total results: 7
- Environmental Sampling and Monitoring Total results: 7
- Environmental testing results Total results: 8
- Exposure to chemicals in the air, soil and water (dioxins) Total results: 18
- Formaldehyde Total results: 1
- Impacts to the environment Total results: 1
- Livestock and pet health impacts Total results: 1
- Odors and toxicity Total results: 2
- Personal Belonging During Cleaning Total results: 6
- Physical work updates, road closures, and upcoming public meetings Total results: 3
- Prior to Cleaning Total results: 3
- Purpose Total results: 6
- Relocation Assistance Total results: 2
- Residential soil sampling and water testing Total results: 10
- Taggart Street Reopening Total results: 12
- Tax-exempt Total results: 1
- Water Management Update Total results: 9
- Emergency Planning and Community Right-to-Know Total results: 301
- Fuel Program Total results: 693
- Great Lakes Funding Total results: 92
- Lead Total results: 398
- MOVES Total results: 57
- Norwood Landfill Site Total results: 30
- Oil Regulations Total results: 96
- Radiation Total results: 1
-
Risk Management Program (RMP)
Total results: 285
- Plan Preparation and Submission Total results: 49
- Applicability/General Duty Clause Total results: 69
- Emergency Response Total results: 6
- Five-Year Accident History Total results: 16
- Offsite Consequence Analysis (OCA) Total results: 57
- Other Risk Management Programs Total results: 35
- Prevention Program Total results: 30
- Program Levels Total results: 16
- RMP*Comp Total results: 7
- Southeast Minnesota Groundwater Total results: 11
Active filters:
Remove all filtersDisplaying 1 - 15 of 81 results
-
How is waste leaving the derailment site tracked?
EPA on-scene coordinators are assigned to track liquid–and solid–waste trucks entering and leaving the derailment site. They log every truck, oversee the loading and covering of waste, truck washing and weighing, and the proper placement of placards. Responders take pictures throughout the process. All trucks go to approved and regulated…
- Last published:
-
What happens after the track work is completed?
The track work has been the highest priority to remove most contamination as early as possible. This, plus preventing the spread of contamination by capturing water from the site and constructing a bypass of Sulphur Run around the site will continue into June. While track work and water management continue…
- Last published:
-
Change of owner and RMP facility ID number
If a facility is sold to a new owner, does it keep its' original RMP Facility ID number? Yes. The facility will keep the ID number assigned by EPA.
- Last published:
-
Facility ID number and re-registering a facility
If a facility deregisters, then reregisters, should the facility use the original RMP Facility ID or will it be assigned a new ID? The facility should use the original ID assigned by EPA.
- Last published:
-
Resubmission of RMP for a facility that previously deregistered
A covered facility deregisters its RMP because it no longer has more than a threshold quantity of a regulated substance in a covered process. If the facility becomes subject to the CAA §112(r) risk management program regulations at a later date and submits a new RMP, should the facility submit…
- Last published:
-
RMP Records Maintained Onsite
Pursuant to 40 CFR Part 68, Subpart G, the owner or operator of a stationary source subject to the risk management program regulations in Part 68 must develop and submit a risk management plan (RMP). Does the owner or operator have to maintain a written copy of the RMP on…
- Last published:
-
What is the definition of “overburdened community” that is relevant for EPA Actions and Promising Practices?
EPA Actions and Promising Practices apply the description of overburdened communities articulated in EPA’s Plan EJ 2014. The term is used to describe the minority, low‐income, tribal and indigenous populations or communities in the United States that potentially experience disproportionate environmental harms and risks due to exposures or cumulative impacts…
- Last published:
-
How will an EPA regional office determine whether a permitted activity impacts a potential overburdened community? What screening tool or process will EPA regional offices use to screen permit applications?
The Agency has developed a nationally consistent screening tool to help identify communities that are potentially overburdened. This tool, known as EJSCREEN, is one of several tools being developed under Plan EJ 2014. EPA anticipates that its regional offices will use EJSCREEN and other readily available information, including known community…
- Last published:
-
Some of the Promising Practices are mentioned in EPA regulations, guidance and recommendations that EPA has issued in the past. So why is EPA issuing the Promising Practices?
EPA is issuing Promising Practices to encourage permit applicants to strategically plan and conduct enhanced outreach to overburdened communities in the permitting process. As some commenters noted, EPA has recommended some of the outreach strategies included in Promising Practices previously. Nevertheless, EPA believes that it is important to issue Promising…
- Last published:
-
Change of Ownership
If a facility that is subject to the risk management program regulations in 40 CFR Part 68 is sold to another owner, is the facility required to make a correction or a full update of its risk management plan (RMP)? If there are no changes in the covered operations at…
- Last published:
-
What does the on-site wastewater treatment process on site entail?
EPA has approved a workplan to allow Norfolk Southern to treat hazardous wastewater on-site, removing vinyl chloride and other contaminants to dispose of the treated wastewater off-site as a non-hazardous waste. Currently, the train derailment site generates nearly one million gallons of wastewater per week from the collection of stormwater…
- Last published:
-
Where is the treated wastewater going?
The wastewater treatment system removes derailment contaminants using several steps, including sedimentation and filtration. The treated wastewater is then tested to verify vinyl chloride is below the drinking water standard. Once treated, water is sent to facilities certified to accept non-hazardous wastewater and that are regulated by federal and state…
- Last published:
-
RMP*eSubmit preparer access
How does a new Preparer get access to a Risk Management Plan (RMP) via RMP*eSubmit? First, the person must register with CDX. To register with CDX, go to https://cdx.epa.gov/ and complete the registration process for a Risk Management Plan “Preparer”. Once set up as a “Preparer”, the Certifying Official needs…
- Last published:
-
Are there health risks to driving through Taggart Street?
There are no anticipated health risks along Taggart Street associated with project activities. As work proceeds, to ensure worker and community safety, the Unified Command will continue to evaluate site conditions for health and safety considerations. While traffic will be able to proceed through the work areas along Taggart Street…
- Last published:
-
How much waste was removed as part of the cleanup efforts?
In late October, EPA announced the completion of major derailment site excavation. Remaining contaminated soil and debris were removed for off-site treatment or disposal. Contact water continues to be treated in an on-site wastewater treatment system prior to removal for off-site disposal. As of November 13, over 174,000 tons of…
- Last published: