Remediation and Restoration Projects for Deer Lake AOC
Project Title | Project Description | Date Completed | Targeted BUI(s) |
---|---|---|---|
Partridge Creek Diversion – Phase 1 | Upstream phase to divert Partridge Creek from the old mine shafts to aboveground daylighted open stream. | 2012 |
|
Partridge Creek Diversion – Phase 2 | Downstream diversion of Partridge Creek out of old mine through to Carp Creek. Included restoration of meandering stream habitat and wetlands. | 2013 |
|
Michigan Department of Environment, Great Lakes,and Energy Partridge Creek Diversion Project Highlight (1 pp, 841 K, About PDF)