EPA RCRA ID: PAD004498010
On this page:
- Cleanup Status
- Facility Description
- Contaminants at this Facility
- Institutional/Engineer Controls
- Enforcement and Compliance
- Related Information
- Contacts for this Facility
Cleanup Status
Note: The EPA is the lead agency for managing cleanups at this facility.
EPA/state will visit the facility and meet with company representatives on an upcoming date. EPA/state is reviewing existing environmental information to determine if further investigation is required. EPA/State will focus first on the health and groundwater impacts, if any, presented by the facility. Once EPA/state completes this review process, an environmental indicator determination will be prepared and posted to this website.
The EPA determined the migration groundwater contamination on was controled September 29, 2021..
Cleanup Actions or environmental indicators characterizing the entire facility are shown below. It is not intended as an extensive list of milestones/activities. This listing, and all the data on this page, come from EPA’s RCRAInfo and are refreshed nightly to this page. For this table and the Cleanup Activities Pertaining to a Portion of the Facility table that follows, a blank in the Status column could mean the action either has not occurred or has not been reported in RCRAInfo.
Cleanup Activities Pertaining to the Entire Facility
Action | Status | Date of Action |
---|---|---|
Human Exposure Under Control Human Exposure Under Control(CA725) | ||
Groundwater Migration Under ControlGroundwater Migration Under Control (CA750) | ||
Remedy DecisionRemedy Decision (CA400) | ||
Remedy ConstructionRemedy Construction (CA550) | ||
Ready for Anticipated Use Ready for Anticipated Use (CA800) | ||
Performance Standards AttainedPerformance Standards Attained (CA900) | ||
Corrective Action Process TerminatedCorrective Action Process Terminated (CA999) |
For definitions of the terms used, hover over or click on the term.
Cleanup Activities Pertaining to a Portion of the Facility
Action | Area Name | Date of Action |
---|
For definitions of the terms used, hover over or click on the term.
Facility Description
Link to a larger, interactive view of the map.
Clairton Plant is located approximately 20 miles south of Pittsburgh in Clairton, Pennsylvania, and sits along the west bank of the Monongahela River. The largest coke manufacturing facility in the United States, Clairton Plant operates nine coke oven batteries and produces approximately 4.7 million tons of coke annually, serving customers in the commercial coke market as well as U.S. Steel’s steelmaking facilities.
Contaminants at this Facility
As documented in the 2013 Consent Order and Agreement (COA), United States Steel Corporation (USS) investigated, determined, and admitted responsibility for areas in the Clairton Plant in which groundwater is contaminated with Benzene, phenols, and other organic compounds and that this contaminated groundwater may be entering Peters Creek and the Monongahela River. An initial February 12, 1987 COA established obligations for USS to remediate and abate these conditions. Since 1990, USS has taken measures to fulfill its obligations via the installation and sampling of numerous monitoring wells, installation and operation of contaminated groundwater recovery systems, installation and operation of an Early Warning System, and installation of a cap and barrier around the Peters Creek Lagoon. The 2013 COA aim is to evaluate and update the groundwater recovery systems. Results and information presented in reports required by the 2013 COA including a Groundwater Site Characterization Report (SCR) and Groundwater Monitoring and Control Work Plan (GWMCWP) along with the most recent First and Second Quarters 2021 Semiannual Compliance Progress Report support the evaluation of this groundwater determination.
Institutional and Engineering Controls at this Facility
The need for Institutional Controls is yet to be determined.
Institutional and Engineering Controls help ensure human exposure and groundwater migration are under control at a cleanup facility. Where control types have been reported by states and EPA in EPA’s RCRAInfo, they are shown below. Not all control types are needed at all facilities, and some facilities do not require any controls. Where there are blanks, the control types may not be needed, may not be in place, or may not be reported in RCRAInfo.
Are Controls in Place at this Facility?
Control(s) Type |
Control(s) in Place? |
Areas Subject to Control(s) |
Documents available on-line: |
|
---|---|---|---|---|
Institutional ControlsNon-engineering controls used to restrict land use or land access in order to protect people and the environment from exposure to hazardous substances remaining in the site/or facility. (CA 772) |
Informational DevicesInformational Devices (ID) |
|||
Governmental Controls (GC) |
||||
Enforcement and Permit Tools (EP) |
||||
Proprietary ControlsProprietary Controls (PR) | ||||
Engineering ControlsEngineering measures designed to minimize the potential for human exposure to contamination by either limiting direct contact with contaminated areas or controlling migration of contaminants. (CA 770) |
Groundwater ControlGroundwater Control (GW) |
|||
Non-Groundwater |
For definitions of the terms used, hover over or click on the term.
Enforcement and Compliance at this Facility
EPA’s Office of Enforcement and Compliance Assurance (OECA) provides detailed historical information about enforcement and compliance activities at each RCRA Corrective Action Site in their Enforcement and Compliance Historical Online (ECHO) system.
RCRA Enforcement and Compliance Reports from ECHO
Related Information
For more information about this facility, see these other EPA links:
- RCRA information in EPA’s Envirofacts database
- Information about this facility submitted to EPA under different environmental programs as reported in EPA’s Facility Registry Services
- Alternative Names for this facility as reported by EPA programs in EPA’s Facility Registry Services
- Cleanups in My Community provides an interactive map to see EPA cleanups in context with additional data, and lists for downloading data
- Search RCRA Corrective Action Sites provides a search feature for Corrective Action Sites
Documents, Photos and Graphics
Contacts for this Facility
EPA Region implements and enforces the RCRA Corrective Action program for and federally recognized tribes.
For further information on this corrective action site, use the Contact Information for Corrective Action Hazardous Waste Clean Ups listings that are accessible through Corrective Action Programs around the Nation.