Testing for Verification of Clean Diesel Technology
Follow these steps for the testing part of the verification process:
1. Develop a test plan and obtain approval.
After completing the Application portion of the process, the manufacturer will select a qualified test facility, work with EPA to develop a test plan, and get approval from EPA for testing.
2. Provide devices to the test facility.
to the test facility:
- A de-greened device (25-125 hrs of operation);
- An aged device (1000 hrs of operation);
- Full sets of installation instructions and operating manual(s); and
- A test engine if the test facility does not have a suitable engine for testing.
3. Conduct testing.
- Ensuring that testing follows the test plan, even if a contract facility conducts the testing;
- Accurately reporting to EPA during testing to resolve any concerns or issues.
If necessary, EPA may observe some or all of the testing.
4. Go to the Evaluation phase.
Once all data, test reports, and associated documentation are submitted to EPA, a technology is evaluated in the final phase of verification.
Click this link or the tab above: Evaluation for the Verification Process.